2026 lead times used as defaults
| Equipment | Typical range (weeks) | Source |
|---|---|---|
| Substation transformer, 5–50 MVA | 75–110 | Terrapin, 2026 |
| Large power / generator step-up transformer, over 50 MVA | 100–150+ | Terrapin, 2026; Wood Mackenzie puts substation transformers above 160 weeks (Data Center Knowledge) |
| Pad-mount transformer | 40–65 | Terrapin, 2026 |
| Medium-voltage switchgear, 15 kV | 52–80 | Terrapin, 2026 |
| Low-voltage switchgear and switchboards | 45–90 | DC Atlas (SourceBlue data) |
| Diesel generator, 1.5–3 MW | 50–78 | Terrapin, 2026 |
| Diesel generator, over 3 MW | 90–110 | Terrapin, 2026 |
| UPS, 500–1,500 kVA | 30–48 | Terrapin, 2026 |
| Modular UPS, 2,000+ kVA | 40–60 | Terrapin, 2026 |
| Automatic transfer switch | 24–40 | Terrapin, 2026 |
| Chiller | 20–85 | DC Atlas (SourceBlue data) |
| Coolant distribution unit (liquid cooling) | about 25 | DC Atlas (SourceBlue data) |
How the order-by date is worked out
Place PO by = energization − install and commission − contingency − manufacturing lead time − submittal approval. Send the RFQ one bid-to-PO period earlier. Float is the number of weeks between today and the RFQ date; negative float means the item is already on the critical path.
What to do when float is negative
- Reserve factory slots with a capacity reservation or partial deposit before the full specification is final.
- Standardize ratings to what vendors have in their production plan, and accept alternate vendors that meet the specification.
- Phase the build so the first data halls energize on the equipment you can get, with the rest following.
- Pre-approve submittals by agreeing designs with the utility and engineer of record early.
- Consider temporary or bridge power for commissioning while permanent equipment is in production.
Frequently asked questions
Are these lead times from order or from approved drawings?
Most vendors quote manufacturing lead time from released, approved drawings. That is why the planner adds submittal approval separately. If your quote runs from purchase order, set submittal approval to zero.
Why is my float negative for transformers?
Large transformers now take two to three years or more. For a site energizing within about three years, the transformer order is usually already critical and needs a reservation or an alternate source now.
Can I add my own equipment?
Yes. Use the empty rows at the bottom of the equipment table for items such as busway, PDUs, cooling towers or battery systems, with your quoted lead times.
Is my project data uploaded?
No. Everything is calculated in your browser and saved only on this device.